
High voltage bushings are among the most critical and failure-prone components in transformers, circuit breakers, and other substation equipment. A single bushing failure can cause transformer explosion, fire, and extended outage. The Tan Delta Tester (dissipation factor analyzer) provides the most effective on-site diagnostic for bushing insulation condition. This article covers specialized tan delta testing techniques for oil-impregnated paper (OIP), resin-impregnated paper (RIP), and resin-bonded paper (RBP) bushings, with detailed guidance on C1/C2 measurement and interpretation.
Bushing insulation degrades due to multiple mechanisms, all detectable by tan δ testing:
Moisture ingress: Through damaged gaskets or porcelain cracks. Moisture increases tan δ dramatically, particularly in C2 (outer insulation).
Partial discharge: Internal voids or delamination create ionization, increasing tan δ with voltage (tip-up effect).
Thermal aging: Prolonged overheating carbonizes paper insulation, increasing C1 tan δ.
Contamination: Surface pollution on porcelain creates leakage currents that artificially inflate tan δ (C2 effect).
Mechanical damage: Cracks or impact damage create pathways for moisture and corona.
Tan δ testing reveals these problems years before catastrophic failure, enabling planned replacement during scheduled outages.
Understanding bushing construction is essential for correct test setup:
C1 (Main insulation): Between the high voltage conductor and the test tap (or flange for non-tapped bushings). This is the primary dielectric barrier.
C2 (Tap-to-ground insulation): Between the test tap and the mounting flange (ground). This outer layer is exposed to environmental effects.
Test tap: A low-voltage terminal accessible on most bushings above 34.5 kV. If unavailable, measure overall insulation (conductor to flange).
Using a tan delta tester, measure C1 and C2 separately using UST (ungrounded specimen test) and GST (grounded specimen test) modes.
De-energize and isolate: Ensure transformer or switchgear is isolated and grounded. Disconnect bushing from overhead lines.
Clean porcelain surfaces: Use isopropyl alcohol and lint-free cloth. Pay special attention to the lower skirt region.
Short the test tap: If testing C1, short the test tap to flange (ground).
C1 measurement (GST mode): Apply test voltage to bushing conductor. Measure tan δ from conductor to ground (flange + tap shorted). This tests the main insulation.
C2 measurement (UST mode): Apply test voltage to the test tap. Measure tan δ from tap to flange (ground). This tests the outer insulation layer.
Overall measurement: For bushings without test taps, measure conductor-to-flange tan δ at multiple voltage levels.
Record temperature: Measure porcelain surface temperature and ambient conditions.
OIP and RIP bushings (per IEC 60137 and IEEE C57.19.01):
C1 tan δ (new): Less than 0.5% at 20°C
C1 tan δ (in-service healthy): 0.3% to 0.7%
C1 tan δ (caution): 0.7% to 1.0% – investigate within 6 months
C1 tan δ (alarm): Greater than 1.0% – plan replacement urgently
C2 tan δ (new): Less than 0.8% at 20°C
C2 tan δ (in-service healthy): 0.5% to 1.0%
C2 tan δ (caution): 1.0% to 1.5% – clean porcelain and retest; if persists, investigate
C2 tan δ (alarm): Greater than 1.5% – surface or internal moisture likely
For resin-bonded paper (RBP) bushings (dry-type, common in switchgear):
Overall tan δ less than 0.8%: Healthy
Overall tan δ 0.8% to 1.5%: Monitor annually
Overall tan δ greater than 1.5%: Plan replacement
Capacitance values are equally important as tan δ for bushing assessment:
C1 capacitance stable (±2%): Normal. No physical change in main insulation.
C1 increasing 2-5%: Possible moisture ingress or insulation compaction.
C1 increasing greater than 5%: Significant moisture – imminent failure risk.
C1 decreasing: Rare; suggests oil loss or gas bubble formation.
C2 capacitance change: Less diagnostic than C1; surface effects dominate.
Always compare capacitance to nameplate values, factory test reports, or previous field measurements. A 3% capacitance change combined with rising tan δ is a powerful failure predictor.
Perform step voltage testing on bushings when feasible. Measure tan δ at 30%, 50%, 70%, and 100% of rated voltage (typically 2 kV to 12 kV for testing).
Tip-up = tan δ(100% voltage) – tan δ(30% voltage)
Interpretation:
Tip-up less than 0.1%: Excellent – no significant partial discharge
Tip-up 0.1% to 0.3%: Acceptable for aged bushings; monitor annually
Tip-up 0.3% to 0.5%: Internal voids or delamination present
Tip-up greater than 0.5%: High risk of internal discharge – immediate investigation
Bushings with significant tip-up but acceptable absolute tan δ may still have developing internal voids. Trend tip-up values over time for early detection.
OIP and RIP bushing insulation follows similar temperature dependence as transformer insulation. Use coefficient k = 0.045 to 0.050 per °C for correction to 20°C.
Quick reference correction factors:
Measured at 25°C → multiply by 0.79 to 0.81
Measured at 30°C → multiply by 0.62 to 0.64
Measured at 35°C → multiply by 0.49 to 0.51
Measured at 40°C → multiply by 0.39 to 0.41
Measured at 45°C → multiply by 0.31 to 0.33
Always use the bushing temperature (porcelain surface + estimated internal gradient). For bushings in direct sunlight, surface temperature may exceed internal temperature by 5-10°C – measure shade-side temperature.
A 230 kV power transformer had four OIP bushings. Annual tan δ monitoring showed three bushings stable (C1 tan δ 0.35-0.42%) and one bushing with C1 tan δ rising: Year 1: 0.38%, Year 2: 0.45%, Year 3: 0.58%, Year 4: 0.72%, Year 5: 0.89%. Tip-up also increased from 0.12% to 0.41%. DGA of transformer oil showed elevated ethylene and methane – signs of thermal stress in the bushing. The utility replaced the bushing during a scheduled transformer outage. One year later, a similar transformer at another substation experienced a bushing explosion that caused a fire, destroying the transformer and costing $8 million. The monitored transformer's bushing replacement cost $120,000 – a 98% cost saving.
C2 (tap-to-ground) tan δ is highly sensitive to surface conditions. Before interpreting C2 readings:
Clean porcelain thoroughly: Use recommended cleaning agents (isopropyl alcohol for light contamination, specialized ceramic cleaners for heavy deposits).
Rinse and dry: Ensure complete drying before testing.
Measure C2 immediately after cleaning: Surface moisture from cleaning can cause false high readings if not fully dried.
Compare cleaned vs. uncleaned values: A significant drop after cleaning confirms surface contamination as the cause, not internal degradation.
For critical bushings, consider performing C2 testing before and after cleaning to document the surface effect.
Establish intervals based on criticality and bushing age:
Critical transformer bushings (generator step-up, transmission): Test annually during transformer outages.
Distribution transformer bushings (below 69 kV): Test every 2-3 years.
Switchgear bushings: Test every 3-4 years.
Bushings over 30 years in service: Test every 6-12 months regardless of voltage.
After lightning strike or through-fault: Test immediately before re-energizing.
Mistake 1 – Testing C1 without shorting the tap: Failing to short the test tap to ground during C1 measurement creates a capacitive divider, producing erratic and unreliable readings.
Mistake 2 – Testing C2 at insufficient voltage: C2 is a thinner insulation layer. Applying full test voltage to the tap may stress the insulation. Use reduced voltage (typically 1-2 kV) for C2 measurements.
Mistake 3 – Ignoring surface leakage: Dirty porcelain dominates C2 readings. Always clean before testing C2, and document cleaning in the report.
Mistake 4 – Not correcting for temperature: Bushing tan δ varies significantly with temperature. Without correction, seasonal trends are meaningless.
Mistake 5 – Testing only one bushing per transformer: Always test all bushings on a transformer simultaneously to compare phase-to-phase consistency. Inconsistent results (one bushing significantly different from others) indicate a localized problem.
Transformer bushings are the second-most common cause of transformer failure (after windings). A bushing failure often destroys the entire transformer – not just the bushing. When marketing tan delta testers, emphasize that bushing monitoring is transformer protection. A $100,000 tan delta tester is trivial compared to a $5 million transformer replacement. Offer free bushing testing templates, C1/C2 trending spreadsheets, and on-site training. Train your sales team to ask: How do you currently monitor your transformer bushings? Then demonstrate how your tester reveals hidden moisture and discharge before they cause catastrophic failure.
High voltage bushings are mission-critical components that deserve dedicated diagnostic attention. Tan delta testing, with proper C1 and C2 measurement, voltage step testing (tip-up), and temperature correction, provides the most sensitive on-site assessment of bushing insulation health. By establishing baselines, trending annually, and applying clear intervention criteria, substation owners can replace deteriorating bushings during planned outages – avoiding the catastrophic transformer failures that often result from bushing explosions. Implement a comprehensive bushing tan delta testing program as part of your transformer maintenance strategy.
Advanced Tan Delta Diagnostics: Frequency Response Analysis and Dielectric Spectroscopy for HV Insulation Assessment
Tan Delta Testing for Medium Voltage Switchgear and Circuit Breakers: Insulation Diagnostics for Distribution Reliability
Tan Delta Testing for High Voltage Bushings: Insulation Diagnostics for Transformer and Switchgear Bushing Reliability
Safety Protocols and Risk Mitigation When Operating Capacitance Delta Testers in High-Voltage Environments